| |
Please visit our links below to see our most recent jobs completed.
|
|
|
|
|
|
Total Clean Video 

|
Total
Clean Demonstration Video
This 8 minute video is a demonstration
of how well the Patented Total Clean System works. This video
will demonstrate rapid dewatering of Sand, Silt, Coal, and Carbon
with flow rates ranging from 800 GPM to 3000 GPM. Even at
these flow rates this system will give you up to 85%
dry solids depending on the type of material, a tough task for competitors
especially with material as small as 400 Mesh.
|
|
Sand Removal
Video

|
Sand Dewatering Project
This video shows how (1) Total Clean
TCW-3000 was utilized to handle flow rates of up to 3000 gpm. The
dredged slurry consisted of sands, silts and organics and was being
removed from a recreational lake in Florida. The sands that
were removed from the slurry were being stockpiled and reused in
the park area. The set up of the unit consisted of (1) scalping
shaker and (4) desanding hydro-cyclone units. The first three units
handled the bulk of the sand load while the 4th unit primarily handled
the finer material. Click
here to see the published article in IDR Magazine.
|
|
USACE
Video


Marina Del Rey Project


|
NEW
Marina Del Rey Sand Dewatering Project
This video shows how CJW Construction
utilized (1) Total Clean TCW-3000 to handle flow rates of up to
3000 gpm. The dredged slurry was pumped 11,000 feet from Marina
Del Rey Harbor and consisted of sands, silts and organics.
The sands that were removed from the slurry were being stockpiled
and reused on the beach. An estimated 70% was reused on the
beach. The contaminated fines overflowed out the back of the
Total Clean into geotubes. The fines will were disposed of
at the landfill. The set up of the unit consisted of (2) scalping
shaker to handle large organics/trash and (4) desanding hydro-cyclone
units.
|
|
Hog Waste Dewatering
 

|
NEW
Hog Waste Dewatering Project
•
Hog
Waste Sludge was pumped to a TCS-1500 via a dredge to the scalping
shaker on the Total Clean. The scalping screen removed the larger
material from the sludge. The majority of sludge passed through
the scalping shaker into the tank. Material from tank was
then pumped through a series of 6 hydrocyclones with 500 GPM capacity
each (total 3000 GPM). We were cleaning at 3 times the feed
rate. Solids where then captured by the DELineator high frequency
linear shakers. Remaining water / solids fall through screen
and are then recycled through the process. Material
coming off the shakers was conveyed to a roller press for additional
dewatering. The average output was 3-5 cubic yards of dewatered
solids per hour and averaged 40-50% solids, they had very little
to no free water from stack. Dewatering of sludge will, in
customers opinion, will become the preferred way to deal with lagoon
solids. The process reduced the water content of material
by 15 times, thus reducing application costs proportionally.
A full production Total Clean has been put into place. To
see this customized system visit our
TCS-1500 Product Page.
|
|
NEW
River Dredging Project
Two TCS-1500 Total
Clean Systems were utilized in series to handle 1500 gpm of dredged
slurry from the river. The contaminated sediment slurry was
pumped by divers from the icy waters of the river to the Total Clean
in subfreezing weather. The Total Clean was enclosed using
2 x 4 framed wall panels covered with reinforced visqueen and heated
using propane space heaters. The temperature on top
of the Total Clean was 70 degrees and would climb to 90 degrees
if the sun came out. The influent into the Total Clean
varied from 5 to 8% solids and the effluent out of the Total Clean
varied from 2500 ppm to 5000 ppm. The effluent was then pumped
to a series of frac tanks where it was then treated with coagulant
and polymer in order to settle out the majority of the remaining
solids. The effluent out of the frac tanks was then pumped
to 0.5 micron sock filters where it was reduced to less than 10
ppm total suspended solids. Initially the effluent out
of the Total Clean was pumped to sand filters and then to sock filters.
The Sand filters had little or no effect due to the fact that the
Total Clean had already removed all the solids down below the particle
size that a sand filter is capable of removing. The additional
frac tanks and polymer addition system were then added to take the
solids loading off of the sock filters.
|


|
Dripping Springs Texas "Dead Man's
Hole Dewatering Project"
DEL utilized one of its Total Clean
Systems in conjunction with two of its 100 cubic foot mobile filter
presses to remove sediment from Dead Man's Hole near Dripping Springs,
TX, just west of Austin. The Total Clean was equipped with
a Scalping Shaker and one Desand/Desilt unit set up with 400 mesh
Screens. Dead Man's Hole is a deep cavernous pool that had been
muddied due to an inflow of sediment from upstream construction
during torrential rains. The constant flow of the waterfall
into the pool continued to re-suspend the powder-like sediment,
turning the pool milky green. American Underwater Services
(AUS) was contracted to provide the diver/dredging operations and
DEL was contracted to remove the sediment from the dredged slurry
and return sparkling clear water to the pool. AUS's divers
had the difficult task of removing the powder-like sediment without
disturbing the natural bottom of the pool. AUS pumped 600-800
gpm of milky slurry to DEL, who then removed the minimal amount
of sand and gravel that was present with the Total Clean.
The rest of the suspended solids (-400 mesh) were removed by the
two Filter presses. As you can see in some of the photos the
effluent that was returned to the pool was sparkling clear as required.
The clarity of the pool prior to the clean-up was less than 1.5
feet and by the time the dredging and filtration operations were
completed the clarity was greater than 9 feet.
|
|
|
|